road-work-headerThe following is a list of highway work that might affect traffic in the Staunton VDOT transportation district during the coming weeks. The Staunton district is comprised of 11 counties, Alleghany, Bath, Rockbridge, Augusta, Highland, Rockingham, Shenandoah, Frederick, Page, Warren and Clarke. Work scheduled is subject to change due to inclement weather and material supplies. Motorists are advised to watch for slow-moving tractors during mowing operations. Also, when traveling through a work zone, be alert to periodic changes in traffic patterns and lane closures.

(NEW) or (UPDATE)  Indicates a new or revised entry since last week’s report.

 

ALLEGHANY COUNTY

Interstate 64

* (UPDATE) Mile marker 0 to 41, eastbound and westbound – Debris removal, clean bridge deck, ditches, shoulders and median. Monday to Friday, 8 a.m. to 5 p.m.

* Mile marker 29 over Route 639, eastbound and westbound. Bridge repairs with intermittent flagger controlled lane closure on Route 639. Work zone is 1.22 miles from Route 60 and to .53 miles of Route 42. Monday – Friday, 7 a.m. to 6:30 p.m. Estimated completion April 12, 2013, weather permitting.

 

Primary Roads

* Route 311 (Kanawha Trail) — Fiber optic cable installations both underground and above ground. Work will include shoulder closures and occasional lane closures. Work zone between the West Virginia Line at Sweet Springs and Route 159 (Dunlap Creek Road) and then continuing on Route 311 north to Route 601 (Tuckahoe Road), then continuing on Route 601 to the West Virginia Line. Estimated work completed June, 2013.

* (UPDATE) Various roads – Brush cutting, shoulder repairs and ditching with flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

 

Secondary Roads

* (NEW) Route 600 – Tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* (UPDATE) Route 617 – Road closed to all traffic from the intersection of Route 616 (Rich Patch Road) and Route 617 (Jamison Mountain Road) to the intersection of Route 616 and Route 618 (Upper Rich Patch Road) – Road widening and safety improvements. Use Route 618 as detour of the work area. Estimated completion is May 31, 2013.

* Route 621 (Roaring Run Road) – Bridge over a tributary to Roaring Run closed until further notice for repairs. This location is .35 mi west from Route 672 (Hooks Mill Lane) and .70 mi south from Route 616 (Rich Patch Road)  Watch for temporary detour with one lane of traffic with stop and proceed when way is clear signs. Estimated completion April 19, 2013, weather permitting.

* Route 633 – Replacement of Cowpasture River bridge and approaches from 1.46 miles south of Route 634 to 1.14 miles south of Route 634. Be alert for flagger traffic control. Estimated completion is May 17, 2013. * Route 647 – Pavement work from intersection with Hattie Street to intersection with Horse Mountain View and Mall Road.  Monday through Friday, 7 a.m. to 5 p.m. Estimated completion November 2013.

* Route 792 – Pavement work from intersection with Horse Mountain View to intersection with Mallow Road.  Monday through Friday, 7 a.m. to 5 p.m. Estimated completion November 2013.

* (UPDATE) Various roads – Shoulder repairs, brush cutting and ditching with flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

 

 

BATH COUNTY

Primary Roads

(NEW) Route 42 – Tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* (UPDATE) Various roads – Pothole repairs, debris removal and shoulder repairs. Flagger traffic control as needed, Monday to Friday, 8:30 a.m. to 4 p.m.

 

Secondary Roads

* (UPDATE) Various roads – Debris removal, grading, pot hole and shoulder repairs, Flagger traffic control. Monday to Friday, 8:30 a.m. to 4 p.m.

 

 

ROCKBRIDGE COUNTY

Interstate 64

* (UPDATE) Mile marker 41 to 57, eastbound and westbound – Debris removal and cleaning of bridge decks, ditches, shoulders and medians. Monday to Friday, 8 a.m. to 5 p.m.

* (UPDATE) Mile marker 45, eastbound and westbound – I-64 bridge repair over Route 629. Intermittent flagger controlled lane closures as need on Route 629 from 2.36 miles to Route 780 and 5.01 miles to Route 60.  Monday – Friday, 7 a.m. to 6:30 p.m.  Estimated completion April 12, 2013, weather permitting.

 

Interstate 81

* (NEW) Mile marker 173 to 185, northbound and southbound – Brush cutting with shoulder closures during daylight hours, Monday to Friday.

* (UPDATE) Mile marker 173 to 205.5, northbound and southbound – Debris removal and cleaning of bridge decks, ditches, shoulders and medians. Monday to Friday, 8 a.m. to 5 p.m.

* (NEW) Mile marker 195 to 200, all northbound lanes closed for I-81 bridge deck work over Route 710 – Truck climbing lane project. On Thursday, April 11 beginning at 8 p.m. until Friday, April 12 at 7 a.m. all I-81 northbound traffic will be detoured as follows:
All northbound traffic will exit I-81 at exit 195 near Lexington and Timber Ridge and travel north on Route 11 to Route 710 and then to the I-81 ramps at exit 200.  Traffic will re-enter I-81 at exit 200 near Fairfield.  Motorists will also have the option of bypassing Route 710 continuing north on Route 11 and re-entering I-81 at exit 213 at Greenville.  Signs will be posted notifying the public of this option.

 

On Friday, April 12 at 7 a.m. until Saturday, April 13 at midnight traffic will use the I-81 northbound lanes to exit 200.  At exit 200 trucks will detour around the I-81 bridge over Route 710 by using the exit ramps at this interchange, crossing Route 710 and then re-entering I-81 using the on-ramps at this interchange.  Signs, traffic devices and flaggers will be used to direct traffic at this location.  Passenger cars and other smaller vehicles will use the left lane until reaching the interchange and will shift to the right lane after trucks have exited, crossing the bridge in the right lane and shifting back the left lane again at the end of the bridge.

 

On Saturday, April 13 at midnight until Sunday, April 14 at 10 a.m. all I-81 northbound traffic will be detoured as follows: All northbound traffic will exit I-81 at exit 195 near Lexington and Timber Ridge and travel north on Route 11 to Route 710 and then to the I-81 ramps at exit 200.  Traffic will re-enter I-81 at exit 200 near Fairfield.  Motorists will also have the option of bypassing Route 710 continuing north on Route 11 and re-entering I-81 at exit 213 at Greenville.  Signs will be posted notifying the public of this option.

 

All work is weather permitting. Tow trucks will be on stand-by in the area to assist with any incidents.
* (UPDATE) Mile marker 201 to 202.5, northbound – Single lane closures for replacement of barriers on Truck Climbing Lane project. Tuesday, April 2 through Thursday, April 4, 8 p.m. to 7 a.m.

 

Primary Roads

* Route 11 (North Lee Highway) – Fiber optic cable installation. Work area between Route 716 (Mt. Atlas Road) and Route 706 (Steeles Fort Road). Estimated completion end of April.

* Route 11 – Pavement work from intersection with Route 760 (Golf Course Road) to intersection with Route 684 (Tinkerville Road). Monday through Friday, 7 a.m. to 5 p.m. Estimated completion November 2013.

* Route 60 (East Midland Trail) – Fiber optic cable installation. Work area between I-81 and City of Buena Vista. Estimated completion end of April.

* Route 60 (West Midland Trail) – Fiber optic cable installation. Work area between Route 850 and City of Lexington. Estimated completion end of April.

* Route 60 (East Nelson Street, City of Lexington) – Bridge over Varner Lane is closed. East Nelson Street traffic from Washington Street to Randolph Street will be rerouted onto Washington Street for the duration of the bridge reconstruction. Watch for detour signs. Estimated completion is Dec. 2013.

* (NEW) Route 130 – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* (NEW) Route 501 – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* (UPDATE) Various roads – Debris pick-up and ditching. Monday to Friday, 8:30 a.m. to 4:00 p.m.

 

Secondary Roads

* Route 629 – Intermittent flagger controlled lane closures as need from 2.36 miles to Route 780 and 5.01 miles to Route 60 for I-64 bridge repair at mile marker 45. Monday – Friday, 7 a.m. to 6:30 p.m.  Estimated completion April 2013.

* (UPDATE) Route 763 (Lincoln Road) at Route 11. Utility project. Install water transmission line on northwest shoulder of Route 763 for 0.60 mile to the intersection of Route 11. Installation will continue on the east shoulder of Route 11 northbound for 1.23 miles. Crossovers may be closed as work progresses. Estimated completion mid-April.

* (NEW) Route 671 (Poplar Hill Road) – Road closure on Tuesday, April 2, 8:30 a.m. to 5 p.m., for pipe replacement. Work area is .05 mile south of the intersection with Route 786 (Stagecoach Lane). No detour will be provided for this closure. Alternate rain/snow dates are April 3 and April 4.

* (NEW) Route 731 – Bridge work over Hays Creek – Abrasive blasting and painting work, April 1 to April 4, 7 a.m. to 7 p.m. Flagger operations as needed.

* (NEW) Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* (UPDATE) Various roads – Sweeping bridges and intersections, pothole repairs, grading, ditching, pipe replacement, tree removal and brush cutting. Flagger traffic control as needed, Monday to Friday, 8:30 a.m. to 4 p.m.

 

 

HIGHLAND COUNTY

Primary Roads

* Route 220 – Shoulder repairs at various locations with flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

* Route 250 – Brush cutting from McDowell to Route 614 with flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

* Various roads – Street sweeping, Monday to Friday, 8:30 a.m.to 4 p.m.

 

Secondary Roads

* Route 678 – Shoulder closure February 18 to April 26 for shoulder improvement project, 1.37 miles south from Route 615 and 1.93 north miles to Route 612. Monday through Thursday, 7 a.m. to 5:30 p.m., with flagger traffic control.

* Various roads – Pothole repairs with flagger traffic control, Monday to Friday, 8:30 a.m. to 4 p.m.

* Various roads – Street sweeping, Monday to Friday, 8:30 a.m.to 4 p.m.

 

 

AUGUSTA COUNTY

Interstate 64 * (UPDATE) Mile marker 96 to 106 on Afton Mountain, eastbound and westbound – Left lane and left shoulder closures for installation of cable barrier/guardrail, Monday, April 1 through Friday, April 5, 9 a.m. to 3 p.m.  Expected completion May 2013.

 

Interstate 81

* (UPDATE) Mile marker 195 to 237, northbound and southbound – Debris removal and cleaning of bridge decks, ditches, shoulders and medians. Monday to Friday, 8 a.m. to 5 p.m.

* (UPDATE) Mile marker 216.5 to mile marker 214.5, southbound – Right lane closure for pavement testing on April 1, 9 p.m. to 6 a.m.  Left lane closure for pavement testing on April 2, 9 p.m. to 6 a.m.

 

Primary Roads

* (UPDATE) Route 11 (Lee Highway, Greenville), northbound and southbound – Single lane closure northbound for sewer construction. March 28 to April 20, 7:30 a.m. to 4:30 p.m. Estimated completion is November 30, 2013.

* Route 340 – Waynesboro, Delphine Avenue Project. Installation of sanitary line and waterline at various locations on Delphine Ave., with retaining wall placement along Delphine Ave. to 4th Street. Be alert for lane closures and flagger traffic control. Work is Monday to Friday, 7 a.m. to 5:30 p.m.

* Various roads – Mowing, pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 8 a.m. to 4:30 p.m.

 

Secondary Roads

* Route 613 (Old Greenville Road) – Road closure for bridge and guardrail work. Work zone is across South River near the Village of Greenville, 0.39 miles east of Route 613 and 0.17 miles west of Route 1201 (Palmer Street). March 25 through April 16, 2013, day and night work hours.

* (NEW) Route 662 – Sanitary sewer work with shoulder closure, March 28 to April 20, 7:30 a.m. to 4:30 p.m.

* Route 1050 – Pavement work from intersection with Route 250 (Jefferson Highway) to cul-de-sac. Monday through Friday, 7 a.m. to 5 p.m. Estimated completion November 2013.

* Route 1316 – Pavement work from intersection with Route 250 (Jefferson Highway) cul-de-sac. Monday through Friday, 7 a.m. to 5 p.m. Estimated completion November 2013. * (NEW) Various roads – Tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

ROCKINGHAM COUNTY 

Interstate 81

* Mile marker 237 to 257, northbound and southbound – Clean debris left side and median, repair signs and ruts. Monday to Friday, 8:30 a.m. to 11:30 p.m.

* Mile marker 240 to 245 southbound – Repair fences. Monday, Tuesday and Friday, 12:30 p.m. to 4:30 p.m.

 

Primary Roads

* Route 11 (South Main Street) from Route 918 (Mill Street) to 0.2 miles south of Route 918 – bridge replacement over North River at intersection with Route 727 (Airport Road). Temporary lane shift (10 foot lanes) for duration of the project. Estimated completion Dec. 6, 2013.

* Route 42 (North Main Street) at the intersection of Route 617 (Church Street) in the town of Timberville.  Intermittent lane closures with flagger traffic control for utility work. Monday through Friday, 9 a.m. to 3 p.m.  Estimated completion end of summer.

* Various roads – Pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 8 a.m. to 4:30 p.m.

 

Secondary Roads

* Route 609 (Naked Creek Road) – Naked Creek Bridge Project. Replacement work at the intersection of Route 603 (Fleeburg Road, Page County) and Route 609. Periodic temporary lane closures, daily, 8 a.m. to 5 p.m. Estimated completion is April 2013.

* Route 617 (Church Street, Town of Timberville) – Utility upgrades with intermittent lane closures controlled by flaggers between Route 42 and Route 1521 (East Riverside Drive). Monday through Friday, 9 a.m. to 3:30 p.m. Estimated completion end of summer.

* Route 727 (Airport Road) – Bridge from Route 11 (Lee Highway) to Route 696 (Kisers Road). Road closed until further notice.

* (NEW) Route 800 (American Legion Drive) closed to traffic beginning April 1 for bridge replacement over North Fork tributary of the Shenandoah River, located northwest of Route 618 (Lone Pine Drive) in Timberville. Estimated completion April 5, 2013.

* Route 918 (Mill Street) will be temporarily closed to traffic from the Route 11 (South Main Street) intersection as part of the bridge replacement work on Route 11 and Route 727 (Airport Road).  Route 918 can be accessed from Route 867 (Old Bridgewater Road). Estimated completion Dec. 6, 2013.

* Route 1421 (Springbrook Road, Town of Broadway) – Road closed over Linville Creek for bridge construction and signal upgrade at Route 42. The closure will be between South Main Street (Route 42) and Early Drive (Route 1415). Watch for detour signage. Estimated completion is April 30, 2013.

* (NEW) Various roads – Tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* Various roads – Pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 7 a.m. to 3:30 p.m.

 

 

PAGE COUNTY

Primary Road

* (UPDATED) Route 211 – Various lane closures for pavement work – Work area between Route 615 (Egypt Bend Road/Longs Road) and Luray city limits. Traffic controlled by flaggers.  Monday through Friday, 7 a.m. to 7 p.m. Estimated completion April 5, 2013.

* Route 340 – Bridge construction work over Compton Creek and Norfolk Southern Railway and approaches, 1.40 miles south of the Page and Warren County lines to 3.50 miles south of the Page and Warren County lines. Daily lane closures with flagger traffic control. Shoulder closures, 24 hours-a-day. Motorists should use extreme caution and obey posted speed limit. Estimated completion is fall 2013.

* Various roads – Pipe installation, patching, brush cutting, shoulder repairs, ditching and grading. Monday to Friday, 7 a.m. to 3:30 p.m.

 

Secondary Roads

* Route 603 (Fleeburg Road) – Naked Creek Bridge Project. Replacement work at the intersection of Route 603 and Route 609 (Naked Creek Road, Rockingham County). Periodic temporary lane closures, daily, 8 a.m. to 5 p.m. Estimated completion is April 2013.

* Route 686 (Smeltzer’s Road) – Compton Creek/Norfolk Southern Railroad Bridge project. New alignment of Route 340 (Stonewall Jackson Memorial Highway). Intersection of Route 686 (Smeltzer’s Road) and Route 340, from 0.24 miles south of the intersection of Route 662 (Compton Hollow Road) at Route 340, is permanently closed. A cul-de-sac will be constructed at the west end of Route 686. Motorists wishing to access Route 686 will need to turn off of Route 340 onto Route 662 and travel 0.26 miles east on Route 662 to the intersection of Route 686. Signs will be posted.

* (NEW) Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

SHENANDOAH COUNTY

Interstate 81

* Mile marker 291 to 302, northbound and southbound – Debris cleanup and mile marker repairs. Monday – Friday, 8:30 a.m. to 4:30 p.m.

* Mile marker 296, northbound – Repair fence. Monday, Wednesday and Friday, 12:30 p.m. to 4:30 p.m.

 

Primary Roads

* Route 11 – Sewer line replacement from Capon Street (Town of Strasburg) to Route 55. Traffic controlled by flaggers. Sunday through Thursday nights, 7 p.m. to 4 a.m. Estimated completion May 17, 2013.

Route 11 at Route 1974 (Holiday Street, Town of Strasburg) – Traffic signal replacement. Estimated completion is April 2013.

Secondary Roads

* Route 629 – Pavement work from intersection of Route 11 (Old Valley Pike) to intersection at Main Street. Monday through Friday, 7 a.m. to 5 p.m. Estimated completion November 2013.

* (NEW) Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

FREDERICK COUNTY

Interstate 81

* (NEW) Mile marker 245 to 247, northbound and southbound – Short duration lane closures at various locations for sign inspections. Wednesday, April 3, 8 p.m. to 4 a.m.

* (NEW) Mile marker 302 to 313, northbound and southbound – Short duration lane closures at various locations sign inspections. Tuesday, April 2, 8 p.m. to 4 a.m.

* Mile marker 302.3, northbound – Right shoulder closures for new sign installation. Monday to Friday, 7 a.m. to 4 p.m. Estimated completion April 30, 2013.

* (UPDATE) Mile marker 307 to 324, northbound and southbound – Clean debris left side and median, Monday, Wednesday, Thursday, Friday, 8:30 a.m. to 11:30 p.m.

* (UPDATE) Mile markers 308 and 317, northbound and southbound – Reset signs Monday to Friday, 8:30 a.m. to 4:30 p.m.

* Mile marker 317, northbound – Extend deceleration lane at Exit 317. Night time lane closures, Monday to Friday, 8 p.m. to 7 a.m., and daytime shoulder closures. Estimated completion is November 2013.

 

Primary Roads

* (NEW) Route 11 – Single lane closures for guardrail removal and replacement. Work area from Route 11 and I-81 intersection to Route 11 in Clearbrook. April 1 to April 6, 7 a.m. to 6 p.m.

* (NEW) Route 50, eastbound and westbound – Short duration lane closures at various locations for sign inspections. Tuesday, April 2, 8 p.m. to 4 a.m.

Secondary Roads

* (NEW) Various roads – Tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

 

CLARKE COUNTY

Primary Roads

No lane closures reported.

 

Secondary Roads

* Route 1014 (Page Street) in the Town of Berryville – Parking lanes on east side of Page Street closed during construction of new of new sidewalk from Liberty Street (Route 1005) to Fairfax Street (Route 1026).  Estimated completion May 17, 2013.

* (NEW) Various roads – Utility tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

 

WARREN COUNTY

Interstate 66

* Mile marker 6 to 13, eastbound and westbound— Clean debris left side and median. Monday, Tuesday and Friday, 8:30 a.m. to 11:30 a.m.

 

Interstate 81

No lane closures reported.

 

Primary Roads

* Various roads – Litter pick up. Monday through Friday.

 

Secondary Roads

* Route 631 (Gooney Manor Loop) from Route 613 to 1.90 south of Route 632. Flagger traffic control for road grading and surface treatment. 7 a.m. to 7 p.m.  Estimated completion July 26, 2018.

* (NEW) Various roads – Tree trimming. Flagger traffic control during daylight hours, Monday to Friday.

* Various roads – Scraping and cleaning pipes and ditches during daylight hours. Monday through Friday.

 

Vegetation management may occur district wide on various routes.

Motorists are reminded to use extreme caution when traveling through work zones.