SCC approves three Dominion solar generation projects


dominion virginia powerThe State Corporation Commission has approved an application by Dominion Virginia Power to construct and operate three solar generation facilities.

Combined, the three projects will contribute 56 megawatts of new renewable energy to the company’s fleet of electric generation facilities.  Over the course of a year, the facilities will produce about 14 megawatts of electricity which equates to an equivalent capacity factor of 25 percent.

The total cost of the three projects is approximately $129.5 million, excluding financing costs.  The company will begin collecting construction costs on September 1, 2016 with the addition of a rate rider to electric bills.  For the average residential customer, the new rider (US-2) will add seven cents to the monthly bill.

Construction of the solar facilities is expected to be completed in December 2016.  The three projects are:

  • Scott Solar – a 17–megawatt facility on a 165–acre site in Powhatan County
  • Whitehouse Solar – a 20–megawatt facility on a 250–acre site in Louisa County
  • Woodland Solar – a 19–megawatt facility on a 200–acre site in Isle of Wight County

In its final order the Commission recognized public policy favoring certain solar projects and stated that, “… the proposed costs of the solar projects are reasonable under the applicable statutes.”



uva basketball team of destiny

Team of Destiny: Inside UVA Basketball's improbable run

Team of Destiny: Inside Virginia Basketball’s Run to the 2019 National Championship, by Jerry Ratcliffe and Chris Graham, is available for $25.

The book, with additional reporting by Zach Pereles, Scott Ratcliffe and Scott German, will take you from the aftermath of the stunning first-round loss to UMBC in 2018, and how coach Tony Bennett and his team used that loss as the source of strength, through to the ACC regular-season championship, the run to the Final Four, and the thrilling overtime win over Texas Tech to win the 2019 national title, the first in school history.

augusta free press

Subscribe

Augusta Free Press content is available for free, as it has been since 2002, save for a disastrous one-month experiment at putting some content behind a pay wall back in 2009. (We won’t ever try that again. Almost killed us!) That said, it’s free to read, but it still costs us money to produce. The site is updated several times a day, every day, 365 days a year, 366 days on the leap year. (Stuff still happens on Christmas Day, is what we’re saying there.) AFP does well in drawing advertisers, but who couldn’t use an additional source of revenue? From time to time, readers ask us how they can support us, and we usually say, keep reading. Now we’re saying, you can drop us a few bucks, if you’re so inclined.

 
augusta free press
augusta free press news