SCC approves Dominion solar projects with performance guarantees to protect customers

Chris Graham

Virginia SCCThe State Corporation Commission (SCC) has approved a petition from Dominion Energy Virginia (Dominion) to build and own two solar generation projects.

As a condition of its approval, however, the SCC required a 20-year performance guarantee to protect Dominion’s customers from the risk of underperformance by the solar generators, which would drive up the costs to customers.

Dominion has proposed to charge customers for the costs of the projects through a rate adjustment clause, or separate rider, on customers’ bills. The power generated by the solar projects will be associated with renewable energy certificates (RECs) that will be purchased by Facebook’s new facility in the Richmond area. The revenue from the RECs will offset the cost to Dominion’s customers charged through the rider.

The SCC contrasted the financial structure of these projects with a Dominion solar project the Commission approved just a few months ago, in which Dominion will purchase the solar power from a third-party vendor through a contract. “With the [purchased-power] model [demonstrated in the Water Strider solar project] … performance risks are typically borne by the third-party vendor, not by customers. With a self-build option as proposed in this petition, Dominion’s customers bear both the performance and financial risks.  Dominion bears little of either.”

The SCC further noted that: “From an economic standpoint, a solar project such as this one has two distinct advantages: there is no fuel-cost risk and there is no carbon-cost risk. Solar, however, under the present state of technology is intermittent and non-dispatchable, so the economic risk is significantly related to its performance at generating electrical power. Simply put, as performance falls short, the cost [to customers] goes up.”

The Commission found that for Dominion’s customers to break even on these projects, the solar facilities must produce a collective capacity factor – the time generating power – of at least 25 percent. Yet, evidence in the record showed that the actual capacity factors of other solar generators in Virginia have been below 20 percent.

The Commission pointed out that customers would bear the costs of underperformance in two ways: customers would have to make up the shortfall in REC revenues from Facebook and customers would bear the costs of energy purchases necessary to make up the shortfall.

To protect Dominion’s customers, the Commission conditioned its approval of these projects on a performance guarantee. The key conditions required by the Commission are:

  • Dominion must guarantee a collective capacity factor performance of at least 25 percent.  In any year in which performance falls below 25 percent, Dominion will bear the additional costs, not customers.
  • The period of the guarantee is 20 years. The Commission pointed out that by the end of the 20-year period more than 75 percent of the costs of the projects will have already been paid through the rider, thus customers are protected from the bulk of the projects’ costs.
  • Any claim of “force majeure” to explain underperformance will be limited to truly extraordinary events such as hurricanes, not just vagaries in weather.

Dominion must accept these conditions to proceed with construction of the solar facilities. During the hearing Dominion proposed a seven-year guarantee.

 

Featured Video

 




Chris Graham

Chris Graham

Chris Graham is the founder and editor of Augusta Free Press. A 1994 alum of the University of Virginia, Chris is the author and co-author of seven books, including Poverty of Imagination, a memoir published in 2019. For his commentaries on news, sports and politics, go to his YouTube page, TikTok, BlueSky, or subscribe to his Street Knowledge podcast. Email Chris at [email protected]. Support AFP by signing up for our newsletter and/or powering our work with a one-time or monthly contribution.

Latest News

justin verlander
Baseball

Where Goochland native Justin Verlander stands on all-time pitching charts

weather water drought temperature advisory
Virginia

Latest from the Drought Monitoring Task Force: Most of still in a drought

The Drought Monitoring Task Force says most of Virginia is still in a drought, which is fine, but they’re telling us that we’re in one here in Waynesboro, and we’re just not. Sorry, I’m not trying to tell the scientists how to do their jobs. But, we’re not. And officially, the Task Force did move...

cyber bullying
Virginia

Hatemailbag: The MAGAs come out in force for Abigail Spanberger

It seems that the MAGAs who like to help us make money by hateposting on our AFP Facebook page are confused about why their electric bills went up this year.

tomato
Local

Media Beat: Big news about a giant tomato plant dominates the headlines

school student child bookbag
Trump's America

Trump tax incentives taking ‘education freedom’ movement nationwide

police investigation
Local

Waynesboro Police offers ‘update’ on Westwood Hills shooting investigation

pit bull dog
Football, Go 'Hoos

UVA Football doesn’t have to pretend to be mad at the dog abuser anymore