Home SCC sets hearing on proposed Dominion Energy project in Charlottesville, Albemarle
Local Government

SCC sets hearing on proposed Dominion Energy project in Charlottesville, Albemarle

Chris Graham
power grid electricity
Photo: © yelantsevv/stock.adobe.com

The State Corporation Commission has set an Oct. 22 hearing to hear from the public on a request from Dominion Energy for approval and certification of an electric transmission facilities rebuild in Charlottesville and Albemarle County.

Project documents from Dominion spell out a $97 million rebuild of 15.8 miles of transmission lines and supporting structures in the city and county, with a proposed start date of Jan. 31, 2028.

The file online with the SCC shows 175 public comments stating a variety of objections to the application – most notably, concerns about impacts on the environment and viewsheds.

The public hearing will be held in the City Council Chambers at City Hall, 605 E. Main St., Charlottesville.

The hearing will begin at 6 p.m. and continue until 10 p.m. or until all registered public witnesses have testified.

People intending to testify as public witnesses should arrive at least 15 minutes prior to the hearing and register with the SCC’s bailiff.

Witness statements will be limited to five minutes.

A telephonic public witness hearing in this case will be held on Nov. 10.

The evidentiary hearing is scheduled for Dec. 2 at the SCC building in Richmond.

Project overview

  • Rebuild approximately 8.7 miles of the existing 230 kilovolt (“kV”) Charlottesville/Hollymeade Junction Line #2054 by removing the existing 230 kV structures, which are mostly single circuit wooden H-frame structures, and replacing them with double circuit 230 kV monopole structures utilizing current 230 kV standards.
  • Install approximately 8.4 miles of idle 230 kV conductors on the vacant circuit of Dominion’s proposed 230 kV double circuit structures between Charlottesville Substation and Hollymeade Junction.
  • Rebuild approximately 7.2 miles of the existing 230 kV Hollymeade Junction-Gordonsville Line #2135 by removing the existing 230 kV structures, wrhich are mostly single circuit wooden H-frame structures, and replacing them with double circuit 230 kV monopole structures utilizing current 230 kV standards.
  • Install approximately 8.4 miles of idle 230 kV conductors on the vacant circuit of Dominion’s proposed 230 kV double circuit structures between Hollymeade Junction and Gordonsville Substation.

Dominion’s case for the project

The project, per the Dominion Energy application, is necessary:

  • to resolve identified NERC reliability violations projected to occur that, if not relieved, will severely impact the transmission system’s ability to maintain reliable service to Dominion’s customers in the Gordonsville Load Area, which is defined generally as the all or part of Albemarle, Culpeper, Fluvanna, Greene, Louisa, western Goochland, northern Cumberland, and Orange counties, the City of Charlottesville, and the Town of Culpeper.
  • to maintain the structural integrity and reliability of the networked transmission system.
  • to ensure Dominion Energy can adequately and reliably provide service for the load growth anticipated in the Gordonsville Load Area.

Costs, timeline

The total estimated conceptual cost of the project is approximately $97 million (in 2025 dollars), which includes approximately $92.5 million for transmission-related work, and approximately $4.5 million for substation-related work.

The desired in-service date is no later than Dec. 31, 2028. Dominion estimates it will take approximately 12 months for detailed engineering, materials procurement, permitting, real estate, and construction after a final order from the SCC.

Dominion requests a final order by Jan. 31, 2027. Should the SCC issue a final order by Jan. 31, 2027, to accommodate long-lead materials procurement, Dominion estimates that construction should begin around Jan. 31, 2028, and be completed by Dec. 31,2028

Multimedia

 




Chris Graham

Chris Graham

Chris Graham is the founder and editor of Augusta Free Press. A 1994 alum of the University of Virginia, Chris is the author and co-author of seven books, including Poverty of Imagination, a memoir published in 2019. For his commentaries on news, sports and politics, go to his YouTube page, TikTok, BlueSky, or subscribe to his Street Knowledge podcast. Email Chris at [email protected].

Latest News

uva football xavier brown
UVA Football

UVA Football: Xavier Brown to join the cast for ‘Coach’s Corner with Tony Elliott’

chicago cubs
Baseball

Michael Schoeffel | In search of Wrigley Magic: A rain delay and a walk-off

There I was in Chicago, having dragged my wife and 5-year-old son there under the pretense of a beach vacation – our AirBnB was only a block from Lake Michigan – but of course the real reason we were there was to see my beloved Cubs.

power grid electricity
State Government

Lawmakers ask Gov. Spanberger to call special session on Dominion-NextEra merger

A group of lawmakers has asked Gov. Abigail Spanberger to call a special session of the General Assembly “to extend the State Corporation Commission's timeframe for reviewing the proposed merger between Dominion Energy and NextEra Energy.”

US capitol washington DC trump congress
Trump's America

Kary Love | Are you a terrorist if you disarm a terrorist? The U.S. government says yes

canada
Trump's America

Lawrence S. Wittner | It’s possible to salvage the Canadian-American friendship

uva football beau pribula
UVA Football

UVA Football: I’d keep the offense vanilla as long as is humanly possible

harrisonburg
Local

Harrisonburg: 19-year-old shot near JMU campus on Saturday night