The third northbound lane of Interstate 81 in the Staunton area will fully open to traffic this week, and you won’t believe how much it’s costing us.
The overall budget for adding an extra lane between mile markers 221.45 and 225.6 is, gulp, $140.5 million.
So, half that?
Remember how I’ve told you that our congressman, Ben Cline, likes to brag about how he was able to convince the Trump administration to sign off on $17 million in new money for I-81 improvements in Virginia?
That money would have a hard time paying for the guys working on this project to take smoke breaks.
The work on this tiny sliver of the 325 miles of Interstate 81 that runs through Virginia began in the 2023, and will continue through next summer, per the folks at VDOT.
Kinda seems to be the case that by the time we get all of the ongoing work on the I-81 corridor done, we’ll either need to start all over again, because of all the increased traffic, or, more likely, roads will be obsolete, because we’ll finally have those flying cars they’ve been promising us since “The Jetsons.”
The challenges with this sliver of I-81 in Staunton and Augusta County include needing to
A release from VDOT tells us that work continues in both directions of the interstate including:
- bridge construction
- final paving and striping
- installation of guardrail and signs
You’ll need to be alert for shoulder closures, traffic-pattern shifts and overnight single-lane closures.
Northbound and southbound I-81 continue to have a work-zone speed limit of 60 miles an hour.