VDOT has updated its schedule for highway work in the Culpeper District during the next week.
Traffic movements may be restricted, and speed limits may be reduced in work zones.
VDOT’s nine-county Culpeper District includes the counties of Albemarle, Culpeper, Fauquier, Fluvanna, Greene, Louisa, Madison, Orange and Rappahannock.
Culpeper District traffic information is available on Twitter at @VaDOTCulp and on VDOT’s website at www.virginiadot.org/travel/travel_alerts/culpeper/default.asp.
Albemarle County
(NEW) Soil borings – Expect lane and shoulder closures in the following areas.
- Route 631 (Rio Road East), mobile, alternating lane closures between Route 650 (Gasoline Alley) and Route 768 (Pen Park Road) in the northbound and southbound lanes, Monday through Friday, 8 p.m. to 6 a.m.
- Route 824 (Patterson Mill Lane), alternating lane closures between U.S. 250 (Rockfish Gap Turnpike and Route 688 (Midway Road) in the eastbound and westbound lanes, Monday and Tuesday, 9 a.m. to 6 p.m.
(NEW) Other construction – Expect lane and shoulder closures in the following areas:
- Interstate 64, right shoulder closures between mile marker 106 and mile marker 107 in the westbound lanes, Monday and Tuesday, 8 a.m. to 3 p.m.
- Interstate 64, right shoulder closures between mile marker 104 and mile marker 105 in the westbound lanes, Tuesday through Thursday, 7 p.m. to 5:30 a.m.
- Interstate 64, right shoulder and left lane closed between mile marker 102 and mile marker 103 in the eastbound lanes, Monday through Thursday, 7 p.m. to 5:30 p.m.
(UPDATE) Ditch cleaning – Expect lane and shoulder closures, 9 a.m. to 3 p.m. in the following areas:
- Interstate 64, alternating lane closures between mile marker 115 and mile marker 117 in the eastbound and westbound lanes, daily through Friday.
- Interstate 64, right shoulder closures between mile marker 107 and mile marker 125 in the eastbound lanes, daily.
- Interstate 63, right shoulder closures between mile marker 113 and mile markers 114 in the westbound lanes, Tuesday and Wednesday.
(NEW) Roadway sweeping – Expect mobile, alternating lane closures, 3:30 a.m. to 6:30 a.m. in the following areas:
- U.S. 250 (Ivy Road), between U.S. 29 (Bypass) and Ednam Drive in the eastbound and westbound lanes, Monday.
- Route 631 (5th Street Southwest), between Route 875 (Sunset Avenue Extended) and the Charlottesville city line in the northbound and southbound lanes, Thursday and Friday.
Signal installations – Expect both shoulders closed, 7 a.m. to 5 p.m., in the following areas:
- U.S. 29 (Seminole Trail), at Route 866 (Greenbrier Drive) in the northbound and southbound lanes, daily.
- Route 20 (Scottsville Road), at Route 712 (Coles Rolling Road) in the northbound and southbound lanes, daily.
Equipment installation – Expect intermittent lane and shoulder closures, nightly, 7 p.m. to 5:30 a.m. in the following areas:
- Interstate 64, between mile marker 105 and mile marker 106 in the eastbound lanes.
- Interstate 64 between mile marker 104 and mile marker 107 in the westbound lanes.
Utility work under VDOT permit – Expect lane and shoulder closures in the following areas:
- U.S. 250 (Rockfish Gap Turnpike), alternating lane closures between Route 240 (Crozet Avenue) and Route 797 (Hillsboro Lane) in the eastbound and westbound lanes, daily, 9 a.m. to 3:30 p.m.
- Route 240 (Crozet Avenue), alternating lane closures between Route 691 (Jarmans Gap Road) and Route 240 (Three Notch’d Road) in the northbound and southbound lanes, daily, 9 a.m. to 3:30 p.m.
- Route 240 (Three Notch’d Road), alternating lane closures between Route 240 (Crozet Avenue) and U.S. 250 (Rockfish Gap Turnpike) in the eastbound and westbound lanes, daily, 9 a.m. to 3:30 p.m.
- Route 751 (Brownsville Road), both shoulders closed between Route 240 (Crozet Avenue) and U.S. 250 (Rockfish Gap Turnpike) in the eastbound and westbound lanes, daily, 9 a.m. to 1:30 p.m.
- Route 797 (Hillsboro Lane), right shoulder closures between U.S. 250 (Rockfish Gap Turnpike) and Route 684 (Half Mile Branch Road) in the eastbound and westbound lanes, daily, 9 a.m. to 3:30 p.m.
(NEW) Interstate 64 – Mowing. Expect mobile, alternating lane closures between mile marker 100 aand mile marker 132 in the eastbound and westbound lanes, daily and nightly, 7 a.m. to 7 a.m.
(UPDATE) Interstate 64 – Tree removals. Expect left lane and left shoulder closures between mile marker 108 and mile marker 109 in the westbound lanes, Wednesday and Thursday, 10 a.m. to noon.
U.S. 29 (Seminole Trail) – Roadway improvements. Expect alternating lane closures between Route 3416 (Angus Road) and Seminole Court in the northbound and southbound lanes, nightly, Monday through Thursday, 9 p.m. to 6 a.m., 10 p.m. Friday to 9 a.m. Saturday, 9 p.m. Saturday to 10 a.m. Sunday, 8 p.m. Sunday to 6 a.m. Monday.
Route 20 (Scottsville Road) – Bridge superstructure repairs/replacement. Expect temporary traffic signal with a traffic pattern shift at Route 708 (Red Hill Road). Route 708 is narrowed to one lane for construction on the bridge over the North Fork Hardware River. Please expect delays during high volume times of the day. Project completion date, Dec. 4, 2024.
(NEW) Route 743 (Advance Mills Road) – Bridge inspection. Expect alternating lane closures with flaggers between Route 605 (Durrett Ridge Road) and Route 1564 (Summer Lane) in the northbound lanes, Tuesday, 8:30 a.m. to 4:30 p.m.
Route 797 (Hillsboro Lane) – Rehabilitation project. Expect alternating lane closures between Route 684 (Half Mile Branch Road) and U.S. 250 (Rockfish Gap Turnpike) in the eastbound and westbound lanes, daily, 9 a.m. to 3:30 p.m.
City of Charlottesville
(NEW) Soil borings – Expect mobile, alternating lane closures, Monday through Friday in the following areas:
- U.S. 250 (Bypass), at Route 3412 (Dairy Road) in the eastbound and westbound lanes, 8 p.m. to 5 a.m.
- Route 3412 (Dairy Road), between Gentry Lane and Route 3412 (Grove Road) in the northbound and southbound lanes, 9 a.m. to 3 p.m.
Roadway improvements – Expect alternating lane closures Monday through Thursday, 9 p.m. to 6 a.m., 10 p.m. Friday to 9 a.m. Saturday, 9 p.m. Saturday to 10 a.m. Sunday, 8 p.m. Sunday to 6 a.m. Monday in the following areas:
- U.S. 250 (Bypass), between Route 3412 (Dairy Road) and the ramp to U.S. 29 (Emmet Street) in the northbound and southbound lanes.
- Route 743 (Hydraulic Road), between Route 3431 (Brandywine Drive) and U.S. 29 (Seminole Trail) in the eastbound and westbound lanes.
Culpeper County
(NEW) Mowing – Expect mobile, alternating lane closures, daily, 8 a.m. to 6 p.m. in the following areas:
- U.S. 29 (James Monroe Highway), between the Madison County line and the Fauquier County line.
- U.S. 211 (Lee Highway), between Route 622 (Old Bridge Road) and Route 613 (Waterloo Road) in the eastbound and westbound lanes.
(UPDATE) Utility work under VDOT permit – Expect lane and shoulder closures in the following areas:
- U.S. 522 (Germanna Highway), between U.S. 522 (Zachary Taylor Highway) and the Culpeper town line in the northbound and southbound lanes, 8 a.m. to 4 p.m.
- U.S. 522 (Zachary Taylor Highway), alternating lane closures between Route 652 (Cedar Grove Road) and Route 3 (Germanna Highway) in the northbound and southbound lanes, Monday through Friday, 8 a.m. to 4 p.m.
- Route 229 (Rixeyville Road), between Route 630 (Jamesons Mill Road) and Route 9537 (Achievement Drive) in the northbound and southbound lanes, daily, 8:30 a.m. to 3;30 p.m.
- Route 667 (Nalles Mill Road), alternating lane closures between Route 699 (Keyser Road) and the Culpeper town line in the eastbound and westbound lanes, daily, starting Wednesday, 9 a.m. to 3:30 p.m.
- Route 667 (Nalles Mill Road), alternating lane closures between Route 699 (Keyser Road) and U.S. 15 Business (James Madison Highway) in the eastbound and westbound lanes, daily, 9 a.m. to 3:30 p.m.
(NEW) Route 628 (Hazel River Road) – Bridge substructure repairs/replacement. Expect alternating lane closures between Route 629 (Settle School Road) and Route 729 (Eggbornsville Road) in the eastbound and westbound lanes, daily, 7 a.m. to 4 p.m.
Route 635 (Hazeland Lane) – Rural rustic repairs. Expect mobile, alternating lane closures between Route 646 (Old Stillhouse Road) and the end of Route 635 in the northbound and southbound lanes.
Fauquier County
(NEW) Paving – Expect alternating lane closures, daily, 7 a.m. to 5 p.m. in the following areas:
- Route 827 (Baldwin Ridge Road), between Route 1407 (North Marigold Court) and the Route 827 dead-end.
- Route 900 (Cavalry Drive), between Route 1338 (Rebel Drive) and Route 673 (Baldwin Street) in the northbound and southbound lanes.
- Route 1335 (Raider Drive), between Route 827 Baldwin Ridge Road and the Route 1335 cul-de-sac in the eastbound and westbound lanes.
- Route 1336 Gray Court), between Route 1335 (Raider Drive) and the Route 1336 cul-de-sac in the northbound and southbound lanes.
- Route 1337 (Wilshire Court), between Route 1336 (Gray Court) and the Route 1337 cul-de-sac in the eastbound and westbound lanes.
- Route 1338 (Rebel Drive), between Route 1337 (Wilshire Court) and the Route 1338 dead-end in the northbound and southbound lanes.
- Route 1345 (Flycatchers Court), between Route 1312 (Auburn Mill Road) and the Route 1345 cul-de-sac in the eastbound and westbound lanes.
- Route 1346 (Forrest Court), between Route 1312 (Auburn Mill Road) and the Route 1346 cul-de-sac in the eastbound and westbound lanes.
- Route 1348 (Nuthatch Court), between Route 1312 (Auburn Mill Road) and the Route 1348 cul-de-sac in the eastbound and westbound lanes.
- Route 1408 (Marlow Court), between Route 1407 (Marigold Lane) and the Route 1408 dead-end in the northbound and southbound lanes.
- Route 1409 (Maple Court), between Route 1407 (Marigold Lane) and the Route 1409 dead-end.
- Route 1414 (Lancaster Drive), between Route 1405 (Nordix Drive) and Route 1457 (Fluvana Court) in the northbound and southbound lanes.
- Route 1431 (Red Maple Court), between Route 1407 (North Marigold Court) and the Route 1431 dead-end in the eastbound and westbound lanes.
- Route 1432 (Walnut Court), between Route 1431 (Red Maple Court and the Route 1432 dead-end in the eastbound and westbound lanes.
- Route 1486 (Kathryn Lane), between Route 1407 (Marigold Lane) and the Route 1486 cul-de-sac in the eastbound and westbound lanes.
- Route 1487 (Christa Court), between Route 1486 (Kathryn Lane) and the Route 1487 cul-de-sac in the eastbound and westbound lanes.
(NEW) Mowing – Expect mobile, alternating lane closure in the following areas:
- Interstate 66, between mile marker 14 and mile marker 37 in the eastbound and westbound lanes, daily and nightly through Monday, 7 a.m. to 7 a.m.
- U.S. 17 (James Madison Highway), between the Warrenton town line and Interstate 66 in the northbound and southbound lanes, daily starting Wednesday, 8 a.m. to 6 p.m.
- U.S. 17 (Marsh Road), between the Stafford County line and Route 687 (Opal Road) in the northbound and southbound lanes, daily starting Friday, 8 a.m. to 6 p.m.
- U.S. 29 (James Madison Highway), between the Culpeper County line and the Warrenton town line in the northbound and southbound lanes, daily starting Wednesday, 8 a.m. to 6 p.m.
- U.S. 29 (Lee Highway), between the Warrenton town line and the Spotsylvania County line in the northbound and southbound lanes, daily, 8 a.m. to 6 p.m.
(UPDATE) Roadway improvements – Expect lane and shoulder closures, nightly, 8 p.m. to 6 a.m. in the following areas:
- U.S. 17 Business (West Shirley Avenue), right through lane and right turn lane closed in the northbound lanes between U.S. 211 (Frost Avenue) and Carriage House Lane, daily, 7 a.m. to 5 p.m.
- U.S. 211 Business (Waterloo Street), right lane and right turn lane closed between U.S. 17 Business (Broadview Avenue) and Sullivan Street in the westbound lanes, daily, 7 a.m. to 5 p.m.
(NEW) Utility work under VDOT permit – Expect lane and shoulder closures, daily and nightly through Friday in the following areas:
- Interstate 66, mobile, alternating lane closures between mile marker 14 and mile marker 37 in the eastbound and westbound lanes.
- Route 55 (John Marshall Highway), alternating lane closures between Route 731 (Cobbler Mountain Road) and Route 729 (Carrington Road) in the eastbound and westbound lanes.
Interstate 66 – Shoulder repairs. Expect mobile, alternating lane closures between mile marker 30 and mile marker 33 in the eastbound and westbound lanes, daily through Friday, 7 a.m. to 3:30 p.m.
U.S. 15 (James Madison Highway) – Other construction. Expect alternating lane closures between the Culpeper County line and Route 621 (Freemans Ford Road) in the southbound lanes, daily, 9 a.m. to 3 p.m.
(NEW) Route 688 (Leeds Manor Road) – Bridge inspection. Expect alternating lane closures between Route 284 (Belle Meade Lane) and Route 757 (Old Markham Road) in the northbound and southbound lanes, Tuesday through Thursday, 9 a.m. to 3 p.m.
Route 802 (Springs Road) – Bridge superstructure repairs/replacement. Alternating lane closures between Route 1133 (Waverly Drive) and Route 682 (Black Snake Road), Monday through Friday, 7 a.m. to 4 p.m.
Route 822 (Distillery Road) – Bridge superstructure repairs/replacement. Road closed between Route 822 cul-de-sac and Route 55 (John Marshall Highway). A temporary road and bridge are in place. Expected completion date is Dec. 2, 2024.
Route 1437 (Suncrest Drive) – Pipe repairs/installation. Expect alternating lane closures between Route 839 (Porch Road) and the cul-de-sac in the northbound and southbound lanes, daily, 9 a.m. to 4 p.m.
Fluvanna County
(NEW) Bridge inspections – Expect alternating lane closures Wednesday through Friday, 9 a.m. to 3 p.m. in the following areas:
- U.S. 15 (James Madison Highway), at Route 672 (Carys Creek Road) in the northbound and southbound lanes.
- U.S. 250 (Richmond Road), between Route 759 (Sunny Field Lane) and Route 707 (Southwinds Court) in the eastbound and westbound lanes.
Louisa County
(NEW) Bridge inspections – Expect alternating lane closures, Monday, 8:30 a.m. to 4:30 p.m. in the following areas:
- U.S. 522 (Zachary Taylor Highway), between Route 208 (New Bridge Road) and Route 1017 (Virginia Way) in the northbound and southbound lanes.
- Route 699 (Indian Creek Road), between Route 640 (East Old Mountain Road) and U.S. 522 (Cross County Road) in the northbound lanes.
(NEW) Utility work under VDOT permit – Expect alternating lane closures in the following areas:
- Route 605 (Shannon Hill Road), between Route 758 (White Walnut Road) and U.S. 33 (Jefferson Highway) in the northbound and southbound lanes, Monday, 9 a.m. to 3 p.m.
- Route 646 (Yanceyville Road), between Route 605 (Shannon Hill Road) and Route 697 (Vigor Road in the northbound and southbound lanes, Tuesday through Thursday, 9 a.m. to 3:30 p.m.
Construction of a new roundabout – Expect alternating lane closures daily, 7 a.m. to 6 p.m. in the following areas. Project anticipated completion date, Jan. 31, 2025.
- U.S. 522 (Zachary Taylor Highway) between Route 623 (Chopping Road) 0.3 miles north of Route 208 (New Bridge Road) in the northbound and southbound lanes.
- Route 208 (New Bridge Road) between U.S. 522 (Zachary Taylor Highway) and Alma Gaynelle Drive in the eastbound and westbound lanes.
(NEW) Interstate 64 – Mowing. Expect mobile, alternating lane closures between mile marker 131 and mile marker 148 in the eastbound and westbound lanes, daily and nightly, 7 a.m. to 7 a.m.
(UPDATE) Interstate 64 – Tree trimming. Expect mobile work zone with right shoulder closures between mile markers 131 and mile marker 143 in the westbound lanes, daily through Friday, 8 a.m. to 4 p.m.
U.S. 15 (James Madison Highway) – Pipe repairs/installation. Expect alternating lane closures between the Orange County line and Zion Crossroads in the northbound and southbound lanes, daily, 8 a.m. to 4 p.m.
Route 640 (East Jack Jouett Road) – Bridge repairs. Road closed between Route 613 (Poindexter Road) and Route 617 (Green Springs Road). Expected completion date is Dec. 6.
Madison County
(NEW) Paving – Expect alternating lane closure, daily, 7 a.m. to 7 p.m. in the following areas:
- U.S. 29 (South Seminole Trail), between Route 634 (Washington Street) and Route 631 (Kirtley Road) in the northbound and southbound lanes.
- Route 231 (South F T Valley Road), between Route 643 (Etlan Road) and the Rappahannock County line in the northbound and southbound lanes.
(NEW) U.S. 15 (James Madison Highway) – Bridge inspection. Expect alternating lane closures at Route 631 (Meander Run Road) in the northbound and southbound lanes, Wednesday through Friday, 9 a.m. to 3 p.m.
U.S. 29 (South Seminole Trail) – New roadway construction. Expect alternating lane closures between Route 677 (Estes Road) and Route 662 (Shelby Road) in the northbound and southbound lanes, daily, 6 a.m. to 6 p.m.
Orange County
(NEW) U.S. 522 (Zachary Taylor Highway) – Bridge inspection. Expect alternating lane closures between Route 719 (Belmont Road) and the Spotsylvania County line in the northbound and southbound lanes, Wednesday through Friday, 9 a.m. to 3 p.m.
Rappahannock County
(NEW) Mowing – Expect lane and shoulder closures in the following areas:
- U.S. 211 (Lee Highway), between Route 48 (Skyline Drive) and Waterpenny Lane in the eastbound and westbound lanes, Monday through Wednesday, 8 a.m. to 2:30 p.m.
- U.S. 522 (Zachary Taylor Highway), between U.S. 211 (Lee Highway) and the Warren County line in the northbound and southbound lanes, Wednesday through Friday, 7:30 a.m. to 12:30 p.m.
(NEW) Route 231 (F T Valley Road) – Paving. Expect alternating lane closures between Route 621 (Yancey Road) and the Madison County line in the northbound and southbound lanes, daily, 7 a.m. to 7 p.m.