road work transportationHighway work in the Lynchburg District requiring road/lane/structure closures is scheduled, weather permitting. Items in italics contain new/updated information. For up-to-date information, call 511 or visit www.511Virginia.org.

Amherst County:

Route 29 Business – Madison Heights, project to replace median barrier. Lane closures will occur. Use caution. Estimated completion – April 2019.

Route 29 Business at Route 130- Crew will replace back plates on signals.

Route 151 (601- county line) – Shoulder widening & rumble strip project through October 28.

Route 663 – Tree cutting through mid-April will create extended delays. Flaggers will assist motorists.

Surface treatment – Contractor crews will be performing work at various locations. Delays likely.

Various – Crews will work surfaces and respond to customer concerns.

Appomattox County:

Route 460 – Crews will maintain/repair pavement messages.

Plant mix treatment – Beginning April 9, contractor crews will be working at various location. Delays likely.

Various – Crews will work surfaces and respond to customer concerns.

Buckingham County:

Route 20 (Rt. 15, Dillwyn to James River Bridge, Albemarle) – Pavement widening with rumble strips, guardrail replacement/upgrades and paving will take place through summer months. Flaggers and pilot vehicles will control traffic.

Route 633 (Andersonville AHQ) – Crew will work shoulders.

Route 644 & 662 (Andersonville AHQ) – Crew will work on Rural Rustic projects.

Surface treatment – Contractor crews will be performing work at various location. Delays likely.

Various – Crews will cut brush, work surfaces and respond to customer concerns.

Campbell County:

Route 24 @ 646 – Crews will construct roundabout and other improvements. Delays possible.

Route 460 Business – Crews will maintain/repair pavement messages.

Route 696 over Flat Creek (944-709) – Closed for bridge replacement 5/29 thru late July. Detour via Routes 24, 692, and 709 back to 696.

Surface treatment and plant mix- Contractor crews will be performing work on various routes. Delays likely.

Various – Crews will work surfaces and respond to customer concerns.

Charlotte County:

Route 604, Phenix AHQ – Crew will trim trees.

Route 604 and 675, Phenix AHQ: Crews will eradicate pavement markings in advance of surface treatment.

Route 695 over Cub Creek (617 – 727) – Closed thru 5/25 for bridge replacement. Detour via 617, 40 and 727 back to 695.

Routes 807 & 820, Craftons Gate AHQ – Rural Rustic projects underway.

Craftons Gate AHQ – Crew will perform shoulder work on various 4-lane primary routes.

Plant Mix operations – Contractor crews will work at various location. Flaggers and pilot vehicles will assist traffic. Delays likely.

Various – Crews will boom axe, work surfaces and respond to customer concerns.

Cumberland County:

Surface treatment operations: Contractor crews will be performing surface treatment work at various location. Delays likely.

Various – Crew will work surfaces, cut brush, repair drainage and respond to customer concerns.

Halifax County:

Route 58 W over Lawson Creek (501-931) – Lane closure, 11’6” width restriction for bridge work. Est. comp. 5/2018.

Routes 58 & 501, Cluster Springs AHQ – Crew will pick up trash.

Route 619 at Hunting Creek – Bridge weight limit lowered to 16 tons.

Route 670 over Buffalo Creek – Road closed from 639-637 for bridge replacement. Detour via 639 to 638 and 637 back to 670. Estimated completion – June 22.

Plant mix treatment – Beginning April 9, contractor crews will be working at various location. Delays likely.

Bethel AHQ – Crew will boom axe on secondary routes and repair shoulders on primary/secondary routes.

Volens AHQ – Crew will cut right of way.

Various–Crews will work surfaces and respond to customer requests.

Lynchburg:

Route 29/460 (Odd Fellows Rd Int. & Odd Fellows Rd., Phase 1)– Vehicles enter/exit road. Temporary lane closures on 460 & Odd Fellows. Est. comp. 8/3/18. Speed – 45 mph.

Liberty Mtn Dr – Ramp to 460 E closed for roundabout project.

Odd Fellows Road –1-way traffic from Perkins St. to Bradley Dr. to widen road for new interchange. 3-month detour in place for northbound traffic (to Mayflower Dr.).

Odd Fellows and Mayflower intersection –Closed to traffic through June 20. Detours in place.

Odd Fellows to US 29 Expressway – Phase II – Project started. Bridge over RR to be closed for approximately 1 yr – date to be announced.

Nelson County:

Plant mix treatment – Contractor crews will be working on various routes. Delays likely.

Surface treatment – Contractor crews will be working on various routes. Delays likely.

Various – Crews will work surfaces and respond to customer concerns.

Pittsylvania County:

Route 29 Chatham Bypass – Contractor working on northbound median shoulder. Lane closure.

Route 29 North (Route 1080 to 40) – Contractor crew will perform plant mix operations. Alternating lane closures in use. Message boards in place.

Routes 609 & 633, Gretna AHQ – Crew will install crossline pipe.

Routes 644 & 800, Rondo AHQ – Crew will work on Rural Rustic projects.

Routes 686 (two sites) and 802– Temp. lane closures during drilling operations starting April 30.

Route 792, Gretna AHQ – Crew will stabilize bank.

Brosville AHQ – Crew will do ditch work.

Kentuck AHQ – Crew will prune trees.

Rondo AHQ – Crew will clean roadsides.

Various –Crews will boom axe, work surfaces/shoulders and respond to customers.

Prince Edward County:

Route 360 – Crew will perform sign maintenance.

Route 604 – Crew will work on curve straightening project near Route 666.

Route 622- Crews will eradicate pavement markings in advance of surface treatment.

Route 691 – Crew will prepare for Rural Rustic project.

Routes 705 & 748 – Crews will surface treatment.

Plant mix treatment –Contractor crews will be working at various locations. Delays likely.

Various – Crew will cut brush, remove debris, work surfaces and respond to customer concerns.

District-wide activities:

Bridge maintenance – Crews will perform maintenance on bridges.

Guardrail maintenance – Crews will do guardrail maintenance.

Latex applications and line painting – Traffic control will be in use at various locations.

Line painting/pavement marking – Crews will address work orders/requests as able.

Pipe rehabilitation – Crews will rehab/replace pipe at various locations.

 
 

 




Featured Video

 

AFP

AFP

Have a guest column, letter to the editor, story idea or a news tip? Email editor Chris Graham at [email protected]. Subscribe to AFP podcasts on Apple Podcasts, Spotify, Pandora and YouTube. Support AFP by signing up for our newsletter and/or powering our work with a one-time or monthly contribution.

Latest News

pete hegseth
Politics

Pete Hegseth, facing impeachment, insists he was just following orders

amy argenbright mugshot construction fraud acso
Local

Judge finds Augusta County realtor Amy Argenbright guilty of two felonies

Augusta County realtor Amy Argenbright was found guilty of two counts of felony construction fraud Tuesday following a two-day trial and a two-week deliberation by Circuit Judge Shannon Sherrill.

uva football
Football, Go 'Hoos

UVA Football: First look at Cal, which is absolutely a must-win game

You think UVA Football is reeling? Cal, this weekend’s opponent, was 7-5 in 2025, but former NFL head coach Ron Rivera moved on from Justin Wilcox, gave a first-time head coach, Tosh Lupoi, the big whistle, and the result has been, the wheels falling off.

horse racing
Sports

Virginia Derby will continue as Kentucky Derby qualifier for the 2027 season

amy argenbright mugshot construction fraud acso
Local

Developing: Amy Argenbright convicted on two felony counts in construction fraud case

uva basketball team
Basketball, Go 'Hoos

UVA Basketball: #6 Virginia set to host Bucknell for late-night JPJ hoops

Nayaliz Inez Scott-Moya
Local

Staunton: Police searching for teen who has been missing since Oct. 18