Work is under way this week on the reconstruction of the Interstate 64 interchange at U.S. 250 at Exit 124 at the top of Pantops Mountain.

Construction crews are installing erosion controls and preparing for construction, including installing drainage systems, in the U.S. 250 median. The speed limit on U.S. 250 through the project has been reduced to 25 miles per hour.

The project will reconstruct the existing Exit 124 diamond interchange as a diverging diamond interchange. The diverging diamond interchange briefly shifts vehicles to the opposite side of the road, eliminating traditional left turns that must cross over oncoming traffic.

The new interchange will improve safety by reducing the number of spots where vehicles could collide and can handle more than 600 left-turn movements per hour, twice the capacity of a conventional interchange.

The $14.3 million cost of the project is dramatically reduced from the cost to reconstruct the interchange as a traditional cloverleaf interchange. No additional right of way is needed and the existing bridges will be used for the new interchange.

During construction lane closures will be limited to nighttime hours, but there will be multiple traffic shifts as the project moves forward and drivers should expect changing traffic patterns during the construction. The project is scheduled for completion in the fall of 2022.

The diverging diamond interchange is one of two projects in the second phase of a six-project package of improvements to Albemarle County roads in a $28.5 million design-build contract awarded to Curtis Contracting Inc. of West Point. Wallace Montgomery of Vienna is providing design services for the projects.

Two projects, the reconfiguration of the I-64 Exit 118 interchange at U.S. 29, and an additional lane from I-64 to the Fontaine Avenue exit from U.S. 29 north, are substantially complete.

The Rio Mills connector road between Rio Mills Road and Berkmar Drive is nearing completion.

The final two projects are roundabouts at U.S. 250 and Route 151 at Afton and at Route 20 (Stony Point Road) and Route 649 (Proffit Road). The U.S. 250 roundabout is in the engineering phase and right of way is being acquired for the Route 20 roundabout.

Construction of both projects will begin later this year.

 
 




Featured Video

 

AFP

AFP

Have a guest column, letter to the editor, story idea or a news tip? Email editor Chris Graham at [email protected]. Subscribe to AFP podcasts on Apple Podcasts, Spotify, Pandora and YouTube. Support AFP by signing up for our newsletter and/or powering our work with a one-time or monthly contribution.

Latest News

school bus arm
Local

Oops: Waynesboro bus driver drops off IEP student on a busy highway a mile from home

ben cline elon musk
Politics, Region

Blogger reminds us of the Ben Cline selfies with Elon Musk, Vivek Ramaswamy

Blogger and AFP contributor Gene Zitver gets the credit for bringing back up for our attention a couple of photos from Ben Cline’s recent past – selfies that the Sixth District MAGA congressman took with Elon Musk and Vivek Ramaswamy.

amy argenbright mugshot construction fraud acso
Local

Augusta County: Judge to issue verdict in Amy Argenbright fraud case on Nov. 10

The legal fate of Augusta County realtor Amy Argenbright remains in limbo following a two-day felony construction fraud trial.

Pat Murphy Milwaukee Brewers
Baseball

Milwaukee Brewers manager Pat Murphy: 0-4 all-time vs. Bridgewater College

pit bull dog
Football, Go 'Hoos

UVA Football: Did Solomon Beebe get on the field last week at SMU?

staunton montique gaston front
Local

Staunton: Montique Treymayne Gaston shooting focus of community walk

jim wood facebook
Local, Politics

Waynesboro: Jim Wood, who survived ‘Pete Buttplug’ by laying low, is running out of time