Home Charlottesville holding information session on Belmont Bridge project on Aug. 11
News

Charlottesville holding information session on Belmont Bridge project on Aug. 11

AFP
Belmont Bridge
Rendering of Belmont Bridge project. Image courtesy City of Charlottesville.

The City of Charlottesville has awarded a $23.6 million contract to Caton Construction Group Inc. for the replacement of the Belmont Bridge.

A Notice to Proceed was granted for June 21 to allow for mobilization, erection of signage, documentation of existing conditions and surveying.

The city will host a virtual community information session on Aug. 11 at 6 p.m. to share information about the upcoming construction activities and timeline for the Belmont Bridge Project. Project team members will be present at the meeting to provide information and answer questions.

Registration information for the information session will be available on the city’s website calendar and on the project website at www.belmontbridge.org.

The best way to stay informed about the Belmont Bridge Project is to sign-up for informational updates by sharing your email address on the project website’s Contact page. In addition, the public is encouraged to subscribe to the City’s Traffic Advisories by visiting www.charlottesville.gov/CityNotes.

Once a Land Disturbance Permit is issued, construction will begin on a temporary public parking lot with an entrance off of East South Street. Utility relocations and the removal of the medians on Avon/9th Street will begin in early August. While Avon/9th Street will remain open throughout construction, traffic alerts will be issued for traffic shifts, flagging operations and temporary lane closures on neighboring streets.

The project will include the following:

  • A replacement bridge that is shortened to approximately 236’ in length and maintains the existing 62’ width
  • Roadway Section on Avon/9th Street between Levy Avenue/Garrett Street and East Market Street intersections will consist of one travel lane in each direction, a protected 7’ wide bike lane in each direction and a 10’ wide pedestrian sidewalk in each direction.  Turning lanes will be added/lengthened at each intersection to maximize efficiency of each signal while maintaining traffic flow.
  • “Old” Avon Street will be closed to vehicular traffic between Garrett Street and East South Street to improve the function and safety of the Garrett Street/Levy Avenue/9th Street intersection for all modes of travel while creating a pedestrian plaza within the former roadway.
  • Enhanced pedestrian lighting and landscaping will be provided along 9th Street between Garrett Street/Levy Avenue and East Market Street.
  • New sidewalk will be constructed along neighboring streets to the project corridor and landscaping will be installed – on East South Street, Old Avon Street, Graves Street and Water Street.
  • Additional new proposed pedestrian features include:
  • a pedestrian passageway under 9th Street south of the railroad,
  • a reconstructed staircase connecting “Old” Avon Street to 9th Street,
  • new staircases from 9th Street to Water Street on either side of the bridge north of the railroad and a mezzanine to cross 9th Street under the bridge

Construction is scheduled to be complete by January 2024. Further project information can be obtained by visiting the project website at www.belmontbridge.org and registering for updates on the Contact page.

Multimedia

 




AFP

AFP

Have a guest column, letter to the editor, story idea or a news tip? Email editor Chris Graham at [email protected]. Subscribe to AFP podcasts on Apple PodcastsSpotifyPandora and YouTube.

Latest News

school crossing sign
Local

Waynesboro Public Schools is in crisis: Making the case for a change at the top

uva soccer
UVA Olympic Sports

Soccer: Virginia plays to 1-1 draw with #23 Oregon State at Klöckner Stadium

Virginia got a late equalizer from Brendan Lambe that enabled the Cavaliers to get a point with a 1-1 draw with #23 Oregon State on Tuesday night at Klöckner Stadium. 

football grades
UVA Football

UVA Football re-enters the national rankings, at #25 in both polls

How dumb college football polls are, really anytime, but particularly after one game: Virginia, which beat the hide off NC State, an ACC contender, is ranked, in the coaches’ poll, below Michigan

Northrop Grumman logo
Local

New group organizes to lead the fight about Northrop Grumman pollution

uva football kam robinson
UVA Football

UVA Football: Kam Robinson ‘ready to roll’ for Norfolk State on Friday night

westwood hills elementary school
Local

Westwood Hills Elementary School to remain closed on Wednesday

dabo swinney clemson
Football

Dabo Swinney is about to read ‘The Guy in the Glass’ to us after a presser