Highway work in the Lynchburg District requiring road/lane/structure closures is scheduled, weather permitting. Items in italics contain new/updated information. For up-to-date information, call 511 or visit www.511Virginia.org.
District-wide activities:
Crews will perform various maintenance activities throughout the district. Many of these operations will be mobile in nature; however, motorists should anticipate slow moving equipment, the presence of staff, and possible lane/shoulder/road closure. Activities include, but are not limited to bridge maintenance, guardrail maintenance, brush cutting, tree cutting/limbing, surface/shoulder work, work orders, mowing, boom axing, drainage repairs/work and roadside cleanup.
Amherst County:
Route 629 over Little Piney River- Weight limit reduced to 13 tons.
Please note districtwide activities above.
Appomattox County:
Please note districtwide activities above.
Buckingham County:
Please note districtwide activities above.
Campbell County:
Route 29 Bus., Altavista –Closed w/detour during bridge replacement. Est. comp. May 2021.
Route 29 Bus., Altavista – Crew will work on pavement messaging.
Route 29 Bus @ 1466 – Construction of right turn lane. Completion – August 21, 2020.
Route 460 Bus @ 739 & 1520 – Crew will work on signals.
Route 622 – Road reconstruction and bridge over Flat Creek. Delays possible. Est. comp. Sept. 2021.
Please note districtwide activities above.
Charlotte County:
Route 652, Craftons Gate AHQ – Rural Rustic project.
Routes 757 & 778 – Crew will replace mainline pipe.
Please note districtwide activities above.
Cumberland County:
Please note districtwide activities above.
Halifax County:
Route 49, Cluster Springs AHQ – Trash removal. Be alert to presence of crew.
Route 58, Cluster Springs AHQ – Crew will boom 2/18-2/21.
Routes 658 & 733 (Cluster Springs AHQ) – Crew will clean pipe.
Route 683 (680-685) – Closed for bridge replacement. Detour 683, VA 360 & 680. Est. comp. – 8/20.
Please note districtwide activities above.
Lynchburg:
Odd Fellows Road –Temporary lane closures, changes in traffic pattern during project.
Nelson County:
Route 794 – Crew will perform drainage work on Rural Rustic project. Flaggers will assist motorists.
Please note districtwide activities above.
Pittsylvania County:
Route 29 S and 58 W, Brosville AHQ – Crew will boom axe.
Route 29, Tightsqueeze – Crew will work on signs.
Route 29 N over Banister River – One lane of traffic only on bridge. Signs and other traffic control alert motorists to this change.
Route 40 over Pigg River – Construction of temporary bridge adjacent to existing structure. 45 mph in work zone. Watch for construction vehicles entering/exiting work zone. Flagging operations occasionally in use. Estimated completion of temporary structure- summer 2020.
Route 642 over Shula Rd – Road narrowed to 11’.
Route 727 @ Fall Creek (745-41) –Closed until 2/28 for culvert repairs. Detour: 745, 719, 744 & 41.
Route 730 over Sandy Creek – Bridge and approach work. Completion October 16, 2020.
Please note districtwide activities above.
Prince Edward County:
Routes 360 and 460 – Crew will boom axe and cut behind guardrail.
Route 622 (360-624) – Closed for bridge, approach work over NSRR. Detour via 622 to 360 to 360B/460E to 724 and 624 back to 622. Est. comp. September 2020.
Please note districtwide activities above.